on 11-03-2009 7:05 AM
Hi Experts,
I have attached a component to an activity as stock item.
I have ensured the purchasing data for material (i have attached a master record):
1) Quantity, 2) UOM, 3) GL account, 4) Purch group and 5) Material group.
Even after this, i have experienced the message CN182 during release of activitiy:
"Activity 0080 cannot be released: Purchasing data is missing"
Reqest guidance
warm regards
ramSiva
Hi
Check the material is having purchaising view or not in material master
shashank
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check the other puchase data like info record/ purchase organization are determined as it is a stock item..Try after filling those columns..
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Let me know why inforecord and Porg are required?
I just want a PR only and donot want a source assigned PR.
-
Just check out below SPRO nod of MM>Purchasing>Source List-->Define Source List Requirement at Plant Level. If the tick mark is here is activiated at plant level than system will ask for source list. Remove tick mark and check.
( Define Source List Requirement at Plant Level
In this step, you define source list requirements at plant level. If a source list requirement exists, you must maintain the source list for each material before you can order it. )
With Regards
Nitin P.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.