on 11-03-2009 5:22 AM
How to arrive to a billing plan in FPLT table with project ID or WBS ID in PRPS table.
Thanks,
Vaishnavi
Joining sales and project systems table using VBKD.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
the common element should be billing plan number
note - you can have billing plan without milestone hence the previous comment is partially correct
The field is FPLNR - this is in FPLT and PRPS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I hope there is no common element in both tables..extract the mile stone data from FPLT and MLST tables and then WBS element data from PRPS and MLST tables (first two gives the mile stone and next two tables gives the WBS element to which mile stone is attached)..
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.