on 11-02-2009 5:39 PM
Dear gurus,
I have set up the material master data and necessary configuration to carry out this process. i then created a production order and released ti which generated the inspection lot. using the inspection lot number i recorded inspection results based on inspection points and then made a usage decision for the lot. I then did a confirmation on the production order using CO11N, it is after this confirmation that the product showed up in QI for the respective plant and storage location.
The problem i need answers to is how do i then get the goods to move from QI to unrestricted use? the movement cannot be done in Qm using the usage decision because unlike in procurement there is no place to enter quantities. i thought that the movememnt to unrestricted would happen with the production order confirmation but it is not happening. Can anyone tell mw how to get the movement from QI to unresticted done?
Regards,
Ottley
Hi
Use QA32/QA11 for both the Inspection Types(03 & 04)
even if you do not do the Usage decisionn for 03 ,04 inspection lot can be created & cleared
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Are you using insp type 03 or 04?
FYI - 03 insp type is not stock relevant. 04 insp type is stock relevant. If you using 04 then with ref to UD system will move stock from QI to UNR.
Hope this helps.
Thanks!!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.