Hi experts,
Is it possible to create the cost estimate(ck11n) of a co product seperately..
Joseph,
No. During cost estimate for Main Co-Product, system should cost the other Co-products also to arrive at the Cost for all the products.
The co-product would have in its BOM- the other Products also, so during cost estimate it would do the costing for the remaining products also.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
>
> Hi prasobh,
>
> I hav a semifinished product which hav 5 components of whcih one is this co product..Can i do an other cost estimate for this co pro...
Joseph,
Is it a Bi-Product or Co-product?
Does the semi-finished and Co-Product materials activated with Co-Product Indicator? Do they have also Joint Production section updated in with Equivalance numbers?
Regards,
Prasobh
>
> Hi peasobh,
>
> Both the semi finished and the co prod hav co prodct indicator and they hav joint prodction section updated wt equalance no:
Joseph,
No. when you are running cost estimate for Main Product, system would also calculate and perform the cost estimate for the co-product also.
If you want to use a fixed cost for the co-product then you can directly enter the standard price and also activate the Fixed price Indicator in the costing 1 view. Now when you run the cost estimate for main proudct the cost of the co-product is picked up based on the standard price maintained and not based on the co-product costing based on equivalance number and the quantity structure.
Hope this clarifies,
Regards,
Prasobh
Prasobh,
I am getting every thing fine for the particular semifinished product....I would like to know whether i can create a material cost estimate for co product or wats the reason y i cant make a cost estimate for a co product...when iam trying to make one pop up window appears telling that thrs no valid production version for this material
Joseph,
Does this CO-product has a BOM & Production version on its own? I dont think so, thats the reason you are getting this message. Whereas when you are doing cost estimate for the Semifinished material, system would do the costing of the co-product also.
I dont understand why you want to do the cost estimate for the Co-product, when this happens automatically when you do for semifinished material.
Regards,
Prasobh
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Co-Product can be costed in two ways
1. Fixed cost co-product
2. costing using apportionment structure
You can also run MRP at co-product level also,provided that
1. In main co-product you must define apportionment structure/source structure
2. Main co-product BOM must contains that material with negative qty and co-product indicator
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.