inconsistency in PS report

Former Member
0 Kudos

Hi all,

There is some inconsistency in the PS reports.Actual overall is coming in the S_ALR_*87013558 at the network level.But it is not summing up at the WBS level i.e cost at network i s 50000 INR ,but at corresponding WBS,it is coming up as 0 INR.What could be the reason behind this?

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

Try running CJEN and then see the report.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Chirald,

Please adjust your value category customizing according to the following

settings

:

1) In transaction CJVC, all yellow and/or red lights have to eliminated

by assigning each cost element/commitment item/statistical key figure

according to the following rules:

1.1) Each cost element/commitment item/statistical key figure should

be assigned to a value category, EVEN if its values should NOT

be updated to table Project Information Database, table RPSCO.

In this case please create an assignment to a value category

and activate its 'suppress' indicator. All values basing on an

assignment to this value category won't be updated to RPSCO.

1.2) Each cost element/commitment item/stat. key figure has to be

assigned exactly once to a value category. Assigning them to

more or less than one value category will lead to unpredictable

results.

1.3) Only

1.3.1) cost elements of the same cost element type,

1.3.2) commitment items of the same item category and

1.3.3) statistical key figures of the same unit of measure

and the same KF category are allowed to be assigned to

one value category. Mixed assignments will lead to

unpredictable results, like mixing costs and revenues in

columns or rows.

2) If all yellow and/or red lights in transaction CJVC are eliminated,

please rebuild the Project Information Database (table RPSCO) by

transaction CJEN. Without this, changes from 1.1)-1.3) won't have

any effect.

3) Please rebuild the assigned values by transaction CJBN.

Could you also review notes51971, 327081, 676123?

Thanks a lot and kind regards,

Enrique