Hi,

I have put original budget on a WBS thorough CJ30.. Now i want to put budget for a particular cost elemtent monthwise for that WBS. How can i do this?

Regards,

Kalpesh

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Dear kalpesh Agrawal,

Cost Element wise Budget is not there in SAP. these are the possiable soluation for your Quarry.

1. Cost Element wise Planning is Possiable, but is different from the Budget.

2. But a valadition for Each Cost Element to Internal Order link, then Create a Budget for Internal Order. in this way you will get

Internal Order Budget based on Cost element.

Revert Back.

Raj

kalpesh_agrawal
Participant
0 Kudos

Hi Raj,

Thanks for reply. Pl tell me,

1. Where can i plan cost element monthwise cost for a WBS?

2. Can monthly budget given to internal order??how to do this??

Regards,

Kalpesh

Former Member
0 Kudos

Hi

Please check transaction Code CJR2

Swapnil Kharul

nitin_patoliya
Active Contributor
0 Kudos

1. Where can i plan cost element monthwise cost for a WBS?

Cj40 you can click on Primary cost & Acitivity Input.

2. Can monthly budget given to internal order??how to do this??

monthly budget is not possible for internal order as well.

Monthy budget i.e. period level is possible at Cost center level.

With Regards

Nitin P.

kalpesh_agrawal
Participant
0 Kudos

Hi Nitin Patoliya ,

Thanks for your reply. Pl tell me how can i give cost centerwise monthly budget??

Regards,

Kalpesh

nitin_patoliya
Active Contributor
0 Kudos

just chekc out KPZ2 & KPZ3 TCodes for the Cost Center budgeting at Perioed level.

With Regards

Nitin P.

nitin_patoliya
Active Contributor
0 Kudos

This features is not available in SAP. As you are looking for Monthly budget, on top of it you are looking for Cost element based budget. You have to go for development as In Std. SAP budget is annual / Overall.

With Regards

Nitin P.

nitin_patoliya
Active Contributor
0 Kudos

This features is not available in SAP. As you are looking for Monthly budget, on top of it you are looking for Cost element based budget. You have to go for development as In Std. SAP budget is annual / Overall.

With Regards

Nitin P.