on 10-31-2009 5:41 AM
Sir,
When I Create Maintenance order there are two options
1- Release order
2- Put in process
What is the difference between these two
If I create the maintenence order and put in process that order the system generate the Maintenence order number also the same when I release the order.
So....what is the difference between these two process.......
Nikhil
Hi
1- Release order :
You need not to relaese the notification.That's by default in Release state.
2- Put in process:When Notification is completed & you want to again process it then you can use this tab.
Please refer following
http://help.sap.com/saphelp_di46c2/helpdata/EN/2d/383d38ed23cf56e10000009b38f842/content.htm
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sir,
The Link provied useful information regarding notification status...
But m still not clear about the order....
When I Create maintenence order directly and Put in process the order and save it The status Shown is Released Similarlywhen I release the order directy the status is again released so what is the difference between these two....
Nikhil
User | Count |
---|---|
105 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.