How to settle Plan expenses values to the Project

Former Member
0 Kudos

Hi,

i have created 1 project which is having 2 stages.

Project started in April 2009 and Ends on Dec -2010

Stage 1 - April 2009 to March 2010

Stage 2 -April 2010 to December 2010

I have made the plan values for expenses of the above two stages.

now i wanted to settled the plan values of 2nd stage to the project. How can i settle plan values to the project?

Kindly provide me the T.code for this.

Thanks

Kishore

Accepted Solutions (0)

Answers (3)

Answers (3)

nitin_patoliya
Active Contributor
0 Kudos

Plan settlemtn is not mandatory, However if we wanted to know what if case and plan project completely witthoug executing actaul cost in that case we does the same..

T code for the same is CJ9E.

With Regards

Nitin P.

0 Kudos

HI...

please explain briefly..How and where did you record your plan values for stage 2?

thanx

pan

Former Member
0 Kudos

Hi

Actual values are settled not planed

T-code for sctual settles is cj88