Warning message : change work hours for Teco Activity

Former Member
0 Kudos

Hi Expert,

We would like to chang the work hours from 50hrs to 10hrs for one TECO activity .

But we receive the following pop-up information, could you let me the reason and what the impact will be happened? Thanks.

" Basic work is copied into forecast work because activity is confirmed."

Thanks and Regards

Shubin

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

the rreason for the error is the configuration for confirmation parameters based on the network type/ plant

this message can be ignored if you have reason to change

change as suggested by Abhinay

I am assuming that you are not using CATS for confirmation - if so you have to revferse CATS entry first and then rebook the correct time

Answers (1)

Answers (1)

former_member214674
Contributor
0 Kudos

Hello,

You have already confirmed activity with 50Hrs, Now its possible to change hours to 10.

To change hours:

-Undo Teco

-Cancel Confimation(CN29)(Be informed this will also reverse cost if anything posted)

-Change hours to 10.

-Confirm and Teco again.

Cheers