Hi Expert,
We would like to chang the work hours from 50hrs to 10hrs for one TECO activity .
But we receive the following pop-up information, could you let me the reason and what the impact will be happened? Thanks.
" Basic work is copied into forecast work because activity is confirmed."
Thanks and Regards
Shubin
the rreason for the error is the configuration for confirmation parameters based on the network type/ plant
this message can be ignored if you have reason to change
change as suggested by Abhinay
I am assuming that you are not using CATS for confirmation - if so you have to revferse CATS entry first and then rebook the correct time
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
You have already confirmed activity with 50Hrs, Now its possible to change hours to 10.
To change hours:
-Undo Teco
-Cancel Confimation(CN29)(Be informed this will also reverse cost if anything posted)
-Change hours to 10.
-Confirm and Teco again.
Cheers
Aby
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.