on 10-30-2009 7:05 AM
Sir,
My question is regarding MTTR and MTBR .....
My Plant timing is from 8:30 to 17:30 now suppose a breadown occurs at 16:30 and the work is completed next day at 10:30 then I want that I should get the MTTR as 3 hours but the system is calculating it as 18 hrs........
one solution proposed was to manually put the breakdown hours while doing TECO.....is there any other way to solve the problem.....
hi
The solution proposed is the only way .
Also kindly check with abaper to create new T code with your logic to define the MTTR and MTBF
regards
thyagarajan