Delete budget from Project

Former Member
0 Kudos

How can i delete all types of budget (Original budget, Supplymentry Budget, Transfer Budget, Release Budget etc) from any Project completely through one command like in Fund management we can do from T-Code OFD7 for Fund center.

Accepted Solutions (1)

Accepted Solutions (1)

nitin_patoliya
Active Contributor
0 Kudos

I think thre is not such T Code in PS Budgeting. Because when you execute all these transaction( Original budget, Supplymentry Budget, Transfer Budget, Release Budget ) there isl checks in system. Whole budgeting process is based on approval. By giving this T Code some one can violate that checks.

Secondnd this Budget is binding one. ( I would say one level higher than Committment because more apporval process is required in it. )

I hope this help to you.

With Regards

Nitin P.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hello

I agree with Nitin. There is no any standard T code for your rerquirement.

You need to reduce or remove the budget figs manually from the project provided you should not have commitments and actuals booked to particular WBS element. In case if commitments (or actuals) are there then you can reduce the budget till the commitment (or actual) value.

Regards

Ashish