on 10-29-2009 2:54 PM
we setup extended classic scenario, and how to set the final flag in GR document for service product type PO item?
the user have role SAP_EC_BBP_RECIPIENT and can not found the final flag in screen, is it need enhancement?
if so, how to handle it? In R3 we can use tcode ML81N for service GR and can do the final GR.
Hi lexx,
In confirmation screen go to the item details screen, there will be a check box at last.
select or check it to do the confirmation as a final confirmation/delivery.
regards,
IGA.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
I test in SRM-EBP and tick this checkbox as "X", but this final entry flag cannot transfer to R3, is it the sap bug?
we need this flag transfer to R3, and the further confirmation is not allow to be created in EBP.
In EBP, the table field is BBP_PDIGP-FINAL_ENTRY, in R3 the table field is ESSR-Final
Hi
I test in SRM-EBP and tick this checkbox as "X", but this final entry flag cannot transfer to R3, is it the sap bug?
we need this flag transfer to R3, and the further confirmation is not allow to be created in EBP, also the budget for PO item's WBS should be released in R3.
In EBP, the table field is BBP_PDIGP-FINAL_ENTRY, in R3 the table field is ESSR-Final.
Hi
In SRM, you will still find the check box for Final delivery/Last delivery in Confirmation screen,
Thanks
Kiran