Hi Experts
I wish to create activities for purchase and install an equipment.
The procurement activity is assigned with the component.
the planned delivery time is specifed (ex: 100 days)
Based on this value, can i get calculated the requirement date for the activity (Ex: today+100days) in stead of manual specification of date for the corresponding activity?
warm regards
ramSiva
Yes you can. Assign materials to your activity. then select the activity, click component overview, select the material. then Goto Edit>Component>Transfer del time--->duration....you can see that activity duration get changed as per the delivery time of the material component.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ahmed
Thanks for your response. This seems to be good feature.
However, i could not get the date corrected for my activity after applying this function.
I have created an activity with normal duration 1day. For the same activity, i have assigned a compnent which has 100days planned del time.
Then i have used 'Transfer Del time --> duration'. But no change.
Could you suggest me right approach?
warm regards
ramSiva