cancel
Showing results for 
Search instead for 
Did you mean: 

Req date for an activity based on planned delivery time of component

Former Member
0 Kudos

Hi Experts

I wish to create activities for purchase and install an equipment.

The procurement activity is assigned with the component.

the planned delivery time is specifed (ex: 100 days)

Based on this value, can i get calculated the requirement date for the activity (Ex: today+100days) in stead of manual specification of date for the corresponding activity?

warm regards

ramSiva

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

Yes you can. Assign materials to your activity. then select the activity, click component overview, select the material. then Goto Edit>Component>Transfer del time--->duration....you can see that activity duration get changed as per the delivery time of the material component.

Former Member
0 Kudos

Hi Ahmed

Thanks for your response. This seems to be good feature.

However, i could not get the date corrected for my activity after applying this function.

I have created an activity with normal duration 1day. For the same activity, i have assigned a compnent which has 100days planned del time.

Then i have used 'Transfer Del time --> duration'. But no change.

Could you suggest me right approach?

warm regards

ramSiva

Former Member
0 Kudos

Thank you Ahmed

This is very useful link. My requirement can be met using this feature.

warm regards

ramSiva

Answers (0)