Hi Gurus,

Does any one have step by step configuration documents on SAP PP-PI?

It will be helpfull if you can share with me.

Regards

Sandip

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Following are the config/IMG setting required for PP-PI processes.

1) Define Distribution Keys

IMG > Production Planning for Process Industries > Master Data > Material List > Item Data > Item Data from related areas > Define Distribution Keys

2) Determine Person responsible for Resource u2013

IMG > Production Planning for Process Industries > Master Data > Resource > General Data > Determine Person responsible

3Define Planner Group-

IMG > Production Planning for Process Industries > Master Data > Master Recipe > Define Capacity Planner

4) Define Capacity Planner u2013

IMG > Production Planning for Process Industries > Master Data > Resource > Capacity Requirement Planning > Determine Capacity Planner

5) Determine Standard Value Parameter u2013

IMG > Production Planning for Process Industries > Master Data > Resource > General Data > Standard Value > Define Parameter

6) Define Setup Groups and Setup Group Categories

Define set up groups and set up categories u2013 /

IMG > Production Planning for Process Industries > Master Data > Master Recipe > Data for operations and phases > Define set up groups and set up group categories

7) Define copy setting between plants-Process

IMG > Production Planning for Process Industries > Process Management > Tools > Define copy setting between plants

😎 Define Set Up Control Recipe destination u2013

IMG > Production Planning for Process Industries > Process Management > Control Recipe/PI sheet > Set up control recipe destination

9Define MRP controller u2013

IMG > Material Management > Consumption based Planning > Master Data > Define MRP controller

10) Special Procurement u2013

IMG > Material Management > Consumption based Planning > Master Data > Define Special procurement types

11) Define Floats (Scheduled Margin Key)-

IMG > Material Management > Consumption based Planning > Planning > Define Floats (Scheduled Margin Key)

12Define Splitting of Forecast requirements for MRP-

IMG > Material Management > Consumption based Planning > Evaluation > Forecast > Define Splittng of forecast requirements of MRP

13) Maintain Correction Factors for Forecast

IMG > Material Management > Consumption based Planning > Planning > Procurement > Maintain Correction factors for forecast

14 Carry out Overall Maintenance of Plant Parameters

Maintaining plant parameters in MRP u2013

IMG > Material Management > Consumption based Planning > Plant Parameters > Carry out overall maintenance of plant parameters

15) Define Planning Horizon

Define Planning Horizon u2013

IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Define Planning Horizon

16) Activate Requirement Planning u2013

IMG > Material Management > Consumption based Planning > Planning > Activate Requirement Planning

17) Define Range of Coverage Profiles (Dynamic Safety Stock)

Range of coverage profile u2013

IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Define range of coverage profile (Dynamic Safety Stock)

18) Define Stock in Transfer and Blocked Stock Availability

IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Stocks > Define Stock in transfer and blocked stock

19) Define MRP Areas

IMG > Material Management > Consumption based Planning > Master Data > MRP areas > Define MRP areas

20) Carry out maintenance of MRP groups

IMG > Material Management > Consumption based Planning > MRP groups> Carry out maintenance of MRP groups

21) Define Scope of total Planning - MRP

IMG > Material Management > Consumption based Planning > Planning > Define Scope of total Planning

22 Define Order Types

Define Order Type-

IMG > Production Planning for Process Industries > Process Order > Master Data > Order > Define Order Type

23Define Order Type Dependent parameters u2013

IMG > Production Planning for Process Industries > Process Order > Master Data > Order > Define Order Type Dependent parameters

24) Define Production Scheduler u2013

IMG > Production Planning for Process Industries > Process Order > Master Data > Bill of Material > Define Production Scheduler

25 Define Checking Control - Process Order

Define Availability Check u2013 Define Checking Control u2013

IMG > Production Planning for Process Industries > Process Order > Operations > Availability Check > Define Checking Control

26) Define Checking Rule for backorder processing u2013

IMG > Production Planning for Process Industries > Process Order > Operations > Availability Check > Define Checking rule for back order processing

27) Define Stock and batch determination for good movement u2013

IMG > Production Planning for Process Industries > Process Order > Operations > Define Stock and batch determination for good movement

28) Specify Scheduling Parameters

Specify Scheduling Parameters u2013

IMG > Production Planning for Process Industries > Process Order > Operations > Scheduling > Specify Scheduling Parameters

29) Define Reduction Strategies

Define Reduction Strategy u2013

IMG > Production Planning for Process Industries > Process Order > Operations > Scheduling > Resource data > Define Reduction Strategy

30) Define Confirmation Parameters

Define Order Confirmation u2013

IMG > Production Planning for Process Industries > Process Order > Operations >

Confirmation > Define Confirmation Parameters

31) Define Valuation of Goods Received

Define valuation of goods receive u2013

IMG > Production Planning for Process Industries > Process Order > Integration > Define Valuation of goods received

32) MRP creation indicator u2013

IMG > Material Management > Consumption based Planning > Planning > Define creation indicator

33) Define safety stock u2013

IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Stocks > Define Safety Stocks

34) Define alternative determination of Production u2013

IMG > Production Planning for Process Industries > Process Order > Operations > BOM selection > Define alternate determination of production

35) Define no. ranges u2013

IMG > Production Planning for Process Industries > Process Order > Master data > Order > Number Ranges > Define number ranges for orders

Madhava

Answers (1)

Answers (1)

Former Member
0 Kudos

Dear Sandip,

Plz find Dhaval's input's on PP-PI

For Process Industry.

Configuration

- Create Order Type for Process Order - T.Code CORN

- Create Order Type Dependent Parameter - T.Code COR4

- Production Scheduling Profile - CORY

- Specify Scheduling Parameter - OPUZ

- Create Control Recipe Destination - O10C

- Create Process Massage Destination - O13C (Optional)

- Create Process Instruction Catagory - O12C (Optional)

Master Data

- Create BOM - CS01

- Create Resource - CRC1

- Create Master Recipe - C201

MRP :- MD61/MD01/MD02/MD03/MD04/MD40/MD41/MD42/MD50.

Production Execution :-

- COR1 - Create Process Order Manual

- COR7 - Convert Plan Order to Process Order

- COR6N/CORZ/CORR - Order Confirmation

- CORS - Cancel Confirmation

- CORT - Display Confirmation

- CO53 - Control Recipe Monitor (Optional)

- CO55/CO60 - Maintain PI Sheet (Optional)

- CO54 - Process Massage Monitor (Optional)

- MB31 - Goods Receipt For Order

- COIK / MB1A / MIGO :- Goods Issue

- KKS1/KKS2 - Calculate Varience

- CO88 - Actual settlement

- COOISPI - Order Information System

Regards

kumar