Hi Gurus,
Does any one have step by step configuration documents on SAP PP-PI?
It will be helpfull if you can share with me.
Regards
Sandip
Hi,
Following are the config/IMG setting required for PP-PI processes.
1) Define Distribution Keys
IMG > Production Planning for Process Industries > Master Data > Material List > Item Data > Item Data from related areas > Define Distribution Keys
2) Determine Person responsible for Resource u2013
IMG > Production Planning for Process Industries > Master Data > Resource > General Data > Determine Person responsible
3Define Planner Group-
IMG > Production Planning for Process Industries > Master Data > Master Recipe > Define Capacity Planner
4) Define Capacity Planner u2013
IMG > Production Planning for Process Industries > Master Data > Resource > Capacity Requirement Planning > Determine Capacity Planner
5) Determine Standard Value Parameter u2013
IMG > Production Planning for Process Industries > Master Data > Resource > General Data > Standard Value > Define Parameter
6) Define Setup Groups and Setup Group Categories
Define set up groups and set up categories u2013 /
IMG > Production Planning for Process Industries > Master Data > Master Recipe > Data for operations and phases > Define set up groups and set up group categories
7) Define copy setting between plants-Process
IMG > Production Planning for Process Industries > Process Management > Tools > Define copy setting between plants
😎 Define Set Up Control Recipe destination u2013
IMG > Production Planning for Process Industries > Process Management > Control Recipe/PI sheet > Set up control recipe destination
9Define MRP controller u2013
IMG > Material Management > Consumption based Planning > Master Data > Define MRP controller
10) Special Procurement u2013
IMG > Material Management > Consumption based Planning > Master Data > Define Special procurement types
11) Define Floats (Scheduled Margin Key)-
IMG > Material Management > Consumption based Planning > Planning > Define Floats (Scheduled Margin Key)
12Define Splitting of Forecast requirements for MRP-
IMG > Material Management > Consumption based Planning > Evaluation > Forecast > Define Splittng of forecast requirements of MRP
13) Maintain Correction Factors for Forecast
IMG > Material Management > Consumption based Planning > Planning > Procurement > Maintain Correction factors for forecast
14 Carry out Overall Maintenance of Plant Parameters
Maintaining plant parameters in MRP u2013
IMG > Material Management > Consumption based Planning > Plant Parameters > Carry out overall maintenance of plant parameters
15) Define Planning Horizon
Define Planning Horizon u2013
IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Define Planning Horizon
16) Activate Requirement Planning u2013
IMG > Material Management > Consumption based Planning > Planning > Activate Requirement Planning
17) Define Range of Coverage Profiles (Dynamic Safety Stock)
Range of coverage profile u2013
IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Define range of coverage profile (Dynamic Safety Stock)
18) Define Stock in Transfer and Blocked Stock Availability
IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Stocks > Define Stock in transfer and blocked stock
19) Define MRP Areas
IMG > Material Management > Consumption based Planning > Master Data > MRP areas > Define MRP areas
20) Carry out maintenance of MRP groups
IMG > Material Management > Consumption based Planning > MRP groups> Carry out maintenance of MRP groups
21) Define Scope of total Planning - MRP
IMG > Material Management > Consumption based Planning > Planning > Define Scope of total Planning
22 Define Order Types
Define Order Type-
IMG > Production Planning for Process Industries > Process Order > Master Data > Order > Define Order Type
23Define Order Type Dependent parameters u2013
IMG > Production Planning for Process Industries > Process Order > Master Data > Order > Define Order Type Dependent parameters
24) Define Production Scheduler u2013
IMG > Production Planning for Process Industries > Process Order > Master Data > Bill of Material > Define Production Scheduler
25 Define Checking Control - Process Order
Define Availability Check u2013 Define Checking Control u2013
IMG > Production Planning for Process Industries > Process Order > Operations > Availability Check > Define Checking Control
26) Define Checking Rule for backorder processing u2013
IMG > Production Planning for Process Industries > Process Order > Operations > Availability Check > Define Checking rule for back order processing
27) Define Stock and batch determination for good movement u2013
IMG > Production Planning for Process Industries > Process Order > Operations > Define Stock and batch determination for good movement
28) Specify Scheduling Parameters
Specify Scheduling Parameters u2013
IMG > Production Planning for Process Industries > Process Order > Operations > Scheduling > Specify Scheduling Parameters
29) Define Reduction Strategies
Define Reduction Strategy u2013
IMG > Production Planning for Process Industries > Process Order > Operations > Scheduling > Resource data > Define Reduction Strategy
30) Define Confirmation Parameters
Define Order Confirmation u2013
IMG > Production Planning for Process Industries > Process Order > Operations >
Confirmation > Define Confirmation Parameters
31) Define Valuation of Goods Received
Define valuation of goods receive u2013
IMG > Production Planning for Process Industries > Process Order > Integration > Define Valuation of goods received
32) MRP creation indicator u2013
IMG > Material Management > Consumption based Planning > Planning > Define creation indicator
33) Define safety stock u2013
IMG > Material Management > Consumption based Planning > Planning > MRP calculation > Stocks > Define Safety Stocks
34) Define alternative determination of Production u2013
IMG > Production Planning for Process Industries > Process Order > Operations > BOM selection > Define alternate determination of production
35) Define no. ranges u2013
IMG > Production Planning for Process Industries > Process Order > Master data > Order > Number Ranges > Define number ranges for orders
Madhava
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Sandip,
Plz find Dhaval's input's on PP-PI
For Process Industry.
Configuration
- Create Order Type for Process Order - T.Code CORN
- Create Order Type Dependent Parameter - T.Code COR4
- Production Scheduling Profile - CORY
- Specify Scheduling Parameter - OPUZ
- Create Control Recipe Destination - O10C
- Create Process Massage Destination - O13C (Optional)
- Create Process Instruction Catagory - O12C (Optional)
Master Data
- Create BOM - CS01
- Create Resource - CRC1
- Create Master Recipe - C201
MRP :- MD61/MD01/MD02/MD03/MD04/MD40/MD41/MD42/MD50.
Production Execution :-
- COR1 - Create Process Order Manual
- COR7 - Convert Plan Order to Process Order
- COR6N/CORZ/CORR - Order Confirmation
- CORS - Cancel Confirmation
- CORT - Display Confirmation
- CO53 - Control Recipe Monitor (Optional)
- CO55/CO60 - Maintain PI Sheet (Optional)
- CO54 - Process Massage Monitor (Optional)
- MB31 - Goods Receipt For Order
- COIK / MB1A / MIGO :- Goods Issue
- KKS1/KKS2 - Calculate Varience
- CO88 - Actual settlement
- COOISPI - Order Information System
Regards
kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.