on 10-28-2009 5:48 AM
Hi,
What is the technical difference between these two RA methods, while sales order is linked to project.
Can any one brief some detail .
Zinni
RA is a methodology and can be used for any cost collector - you can see various posts or go to SAP help to understand what RA is.
When Sales Order is a cost collector then you can use RA on sales order
When Project is a cost collector then you use RA on WBS element
By cost collector I mean the object that is being used to collect all costs (and revenue)
When project is linked to sales order then the project object is used as a cost collector, hence RA on sale sorder is not required
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.