Former Member
0 Kudos

Hi,

What is the technical difference between these two RA methods, while sales order is linked to project.

Can any one brief some detail .

Zinni

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

RA is a methodology and can be used for any cost collector - you can see various posts or go to SAP help to understand what RA is.

When Sales Order is a cost collector then you can use RA on sales order

When Project is a cost collector then you use RA on WBS element

By cost collector I mean the object that is being used to collect all costs (and revenue)

When project is linked to sales order then the project object is used as a cost collector, hence RA on sale sorder is not required

Former Member
0 Kudos

Thanks Virendra,

Got answered. This type of clarification is very difficult while going through the sap help.

Zinni