on 10-28-2009 5:41 AM
Hi Friends
I have the following scenario:
Against a delivery for 100 pcs, I have created a TO with 3 line items for 50, 30, 50 pcs.The line items 1 & 3 are confirmed, 2nd line item is pick confirmed, delivery is in complete status, PGI is posted.
Now I want to cancel the 2nd line item.Since the line item is pick confirmed, I shall confirm it and then reverse the movement with another new TO.But since the delivery is complete I cannot create new TO with the SU against this delivery and in document flow for the delivery it will always show that TO was for 130 pcs as there is no link between new TO and old delivery.
Please guide me on how to solve this issue by creating a return TO with storage unit against delivery.
Thanks
Prasad
Cannot you cancel the 2nd line item by LT15? If not, try LT0G.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check OSS note 436644.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.