on 10-28-2009 3:59 AM
Dear PS Gurus,
When we perform the trnsaction CAT2 i'm unable to see the asigned network activities in the work list for copy to enter the tme sheet,
Any one has any idea on why i can't see the activites on the work list
Your help is greatly appriciated
Regards
Srinivsa
Hi Gokul
did you get an answer to this? how did you solve this problem?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Check field selection in tran CAC2
SHASHANK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This is based on the settings of the data entry profile, Please check the customizing of the data entry profile in worklist section,
It should have ticked with worklist, from resource planning , in process, By work Center etc.
With regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.