on 10-27-2009 3:08 PM
Sales order is created with Make-to-order configurable material
Variant. During the planning process, the raw material is issued from
one facility to the facility specified on the sales order using STO
process.
During CTP process (backward & reverse strategy setting,), while doing
the backward scheduling, system considers the transport duration from
the transportation lane and calculates the correct requested date for
the raw material.
If there is no capacity available to make the raw material on the
requested date system is expected to carry out forward scheduling. The
system then updates the planned order that consumes raw material correctly.
While updating the Preq the system does not consider the transport
duration from the transportation lane. The availability date on PurRqs
and the requested date on the PReqRel is same.
Has anybody seen this issue?
Kedar
Hello
i have exactly the same issuce. Can you tell me in detail what you have done?
BR Lisa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
On maintaining the Handling and Transportation resource the issue got resolved.
Kedar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Guys,
We found that the transportation time is considered in forward scheduling of a PReq when we have a transportation resource. But it is not considered when we have GR/GI time in product master or in Tlane(only the GR).
Has anybody gone through this issue?
Kedar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.