Trans duration not consider during Preq forward scheduling

Former Member
0 Kudos

Sales order is created with Make-to-order configurable material

Variant. During the planning process, the raw material is issued from

one facility to the facility specified on the sales order using STO

process.

During CTP process (backward & reverse strategy setting,), while doing

the backward scheduling, system considers the transport duration from

the transportation lane and calculates the correct requested date for

the raw material.

If there is no capacity available to make the raw material on the

requested date system is expected to carry out forward scheduling. The

system then updates the planned order that consumes raw material correctly.

While updating the Preq the system does not consider the transport

duration from the transportation lane. The availability date on PurRqs

and the requested date on the PReqRel is same.

Has anybody seen this issue?

Kedar

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hello

i have exactly the same issuce. Can you tell me in detail what you have done?

BR Lisa

Former Member
0 Kudos

On maintaining the Handling and Transportation resource the issue got resolved.

Kedar

Former Member
0 Kudos

Guys,

We found that the transportation time is considered in forward scheduling of a PReq when we have a transportation resource. But it is not considered when we have GR/GI time in product master or in Tlane(only the GR).

Has anybody gone through this issue?

Kedar