In project profile there is an indicator integrated Planning. What does it mean?. And in what cases do we use integrated planning?

Please answer my query.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

this integrates CO planning with the PS plans

for example the actvity hours used are integrated to CO planning

Former Member
0 Kudos

This message was moderated.

virendra_pal
Active Contributor
0 Kudos

read Nitin's comments - they are spot on

Answers (2)

Answers (2)

Former Member
0 Kudos

closed

former_member230675
Active Contributor
0 Kudos

integrated planning is mainly used where the cost center planning exists, in order to synchronize both project planning and cost centre planning.

nitin_patoliya
Active Contributor
0 Kudos

F4 will give you most of your answer.

This indicator specifies whether an order/project participates in integrated planning or not. You define this per project profile for projects in Customizing:

Activity inputs planned in a plan-integrated order/project are updated directly on the sending cost center if 'Integrated planning with Cost Center Accounting' is activated in the version. You can then also settle plan-integrated orders/projects to cost centers.

For the explaning this concept in IDEAS PLM230 there is small excercise, just check it out.

Plan data is passed on to the profit center and the extended general ledger if both 'Integrated planning with Cost Center Accounting' and the "Integrated planning" indicator are activated in the version.

This is more helpful in the cases where you wanted to updated the costcenter with hours planned on project..

WQith Regards

Nitin P.