Default creation of Top Level WBS

Former Member
0 Kudos

Hi Experts

It is essential to create Top Level WBS with similar key as like Project definition.

Can we get this automatically created while creating project definition using CJ20N?

Warm regards

ramSiva

Accepted Solutions (0)

Answers (3)

Answers (3)

virendra_pal
Active Contributor
0 Kudos

use BADI PROJECTDEF_UPDATE

method AT_SAVE

you can try this to create a subsequent top level WBS after creation of project

while using template is a good option it is not flexible and does not cover all situations

Makal
Active Contributor
0 Kudos

Dear Virendra

Can you elaborate more on this line please?

while using template is a good option it is not flexible and does not cover all situations

Thanks & Regards

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi Shashank

Thnks for your response.

I am aware of this feature.

But is it not useful, because you can not ask user to create WBS in CJ11 and then move to CJ20N for creating rest of the structure .

We must use the transaction CJ20N for building project structure.

In this context, please advise me whether we can get the top level WBS created automatically when creating project definition.

warm regards

ramSiva

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi,

I agree with what Shashank has to say. In case you want the top level WBS to be same as the Project Definition you can have Standard template created and ask the users to create a project by copying. This is the only way your requirement can be fulfilled.

Regards,

Gokul

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Agree with Shashank. I don't think that this can be done automatically.

You can use Special Characters in OPSK but that will be applicable for WBS elements only and not for project definition.

Regards

Ashish