on 10-27-2009 6:22 AM
Hi Experts
It is essential to create Top Level WBS with similar key as like Project definition.
Can we get this automatically created while creating project definition using CJ20N?
Warm regards
ramSiva
use BADI PROJECTDEF_UPDATE
method AT_SAVE
you can try this to create a subsequent top level WBS after creation of project
while using template is a good option it is not flexible and does not cover all situations
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Shashank
Thnks for your response.
I am aware of this feature.
But is it not useful, because you can not ask user to create WBS in CJ11 and then move to CJ20N for creating rest of the structure .
We must use the transaction CJ20N for building project structure.
In this context, please advise me whether we can get the top level WBS created automatically when creating project definition.
warm regards
ramSiva
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.