Relation between progress and stastical key figure

Former Member
0 Kudos

Dear Experts,

Is there any relation between progress and stastical key figure?

If there please let me know.

Thanks in advance.

Best Regards,

Punith.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Punith Reddy Ma... ,

SKF is not way related to RA Key, It is not related to Percentage of Completion also; as per as my knowledge. what is your exactly problem let me know;

Regards

Raj

Former Member
0 Kudos

Hi Raj,

I am new to PS functionality. I am testing one functional module for "Progress Read" and its not woring fine. As I reported the issue, I got an reply saying relation with SKF should be configured first.

Even, I believe there is SKF and progress were different.

Rgds,

Punith.

Answers (1)

Answers (1)

Former Member
0 Kudos

HI

You define the statistical key figures in which the percentages of completion (POCs) are recorded. You make the settings per controlling area.

A statistical key figure must be assigned so that you can evaluate the POC in reporting.

Former Member
0 Kudos

Can anybody tell me, whr do we maintain SKF for result analysis,Aggregated and Non agree gated.

thnx in adv.

ashis

Former Member
0 Kudos

Hi,

Try T-code KK01

Regards,

Gokul

Former Member
0 Kudos

but there i can't see that.

Regards

ashis

Former Member
0 Kudos

Hi,

Try KBH1, KBH2 & KBH3. Hope this helps...