on 10-26-2009 9:55 AM
Dear All
I'm trying to schedule the project using bottom up forward planning with free scheduling option but my project definition dates does not change using scheduling from planning board. It works correctly when i schedule from CJ20N. Please advise.
Thanks
Atif
Hi Atif,
Please do the below step and check wheather it works,
Open project in CJ2B, adjust the dates to your requirement.
Before doing the scheduling, goto Edit -> Reconcile dates -> Extrapolate dates (click). After clicking on Extrapolate dates, the project definition dates will get updated.
Best Regards,
Punith.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Atif12,
The scheduling result should be the same, if your run CJ2B (project planning board) directly or you run CJ20N and then navigate to project planning board.
Please check with button 'options...' in project planning board, if for both cases the scheduling parameters are same or not.
You can search notes using the hotpackage information of your system. If you still donot find a solution, you can open a customer message to let SAP check it.
Kind regards,
Zhenbo