on 10-26-2009 8:08 AM
HI Team,
As we are taking the Detail scheduling run, the planned orders are getting shifted inside the PTF.
We are having Top down heuristice for the DS run.
Can aybody suggest the ways to stop this.
Regards,
Rajesh Satope
Hi,
I haven't faced this situation before. But One way of avoiding this is to maintain a positive value for 'Scheduling Offset' in the strategy tab in minutes equivalent to the planning time fence. But there might be a better way to resolve this issue.
Regards,
Senthilrajan