cancel
Showing results for 
Search instead for 
Did you mean: 

Error - Standard

Former Member
0 Kudos

Dear Experts,

I created a Standard WBS Template and few Standard Networks to be use as a refernce template to create Operative Projects. Further i link standard networks with standard WBS elements by giving WBS reference in Standard network header.

But when i copy and create a Project using the Standard WBS Template only WBS elements are getting created. Though the Standard Networks are link to the template those are not getting copied.

Please guide me on this.

Thanks,

Dileepa.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Dileepa,

While creating Project by copying from template, there will be a check box " With Activities".Have to checked that option?

Former Member
0 Kudos

Dear Ravi,

I did test that, but still activities did not get copied.

Thanks,

Dileepa,

Former Member
0 Kudos

This message was moderated.

virendra_pal
Active Contributor
0 Kudos

template profile is not used for that purpose

check your std network

you have mentioned that the WBS number hs been added to the header

is your network type account assigned - I believe it is

In the std network template you need to assing the relevant WBS number for each activity

now follow the creation using CJ20N etc with activities

Answers (2)

Answers (2)

Former Member
0 Kudos

Have you released both the standard structures? If you have already released standard templates, try copying a network from the standard network template and check what happens.

Let us know if this works.

Regards,

Ajinkya

Former Member
0 Kudos

This message was moderated.