Hello,

we implemented cProjects and using it with the PS for the accounting. After a sometimes hard time of configuration this works fine.

There is still a strange behavior and maybe someone can tell me if it is right or not.

When we change e.g. the status of a task in cProjects to closed this has no influence to the PS element.

Do you have the same "problem" in your configuration or am I doing something wrong with it?

Thank you,

Vanessa

Accepted Solutions (1)

Accepted Solutions (1)

former_member201206
Active Contributor
0 Kudos

Hi Vanessa,

The reason is simple, such status-synchronisation functionality is unfortuenately not implemented in the cProject 4.0 and 4.5.

See the longtext of note 927960.

I think, a sub-system can be implmented to realize this functionality.

Kind regards,

Zhenbo

former_member184588
Active Participant
0 Kudos

Hello Zhenbo,

thank you very much for your answer. Like you suggested I will try to implement a sub-system.

Thanks,

Vanessa

former_member201206
Active Contributor
0 Kudos

Hi Vanessa,

a Protoype will be available in the next days.

KInd regards,

Zhenbo

former_member209919
Active Contributor
0 Kudos

Hi Zhenbo,

My client has the same requirement as Vanessa's client. What have you meant with 'the prototype will be available''? Is SAP development this requirement like a new functionality?

Thanks for the news!!!

Sara

former_member201206
Active Contributor
0 Kudos

It is available now, please see my other thread.