on 10-23-2009 7:11 AM
Hello,
we implemented cProjects and using it with the PS for the accounting. After a sometimes hard time of configuration this works fine.
There is still a strange behavior and maybe someone can tell me if it is right or not.
When we change e.g. the status of a task in cProjects to closed this has no influence to the PS element.
Do you have the same "problem" in your configuration or am I doing something wrong with it?
Thank you,
Vanessa
Hi Vanessa,
The reason is simple, such status-synchronisation functionality is unfortuenately not implemented in the cProject 4.0 and 4.5.
See the longtext of note 927960.
I think, a sub-system can be implmented to realize this functionality.
Kind regards,
Zhenbo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Zhenbo,
this looks really great. Thanks a lot for this.
Have a nice day,
Vanessa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
11 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.