on 10-23-2009 5:26 AM
Hi All,
We are using SRM 5.0 ECS.
Once the shopping cart is created for stock materials it creates reservation in R/3 system.Could you please let me know how it considers movement type once the account assignment is given as Order or Cost centrei.e. either it should take 261 or 201. Where is validation wriiten for this? Is it using any BADI or any configuration involved?
Regards
Answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
As per SRM standard , IN ECS you can not make a Reservation. However you may implement a badi. check it up
br
muthu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use badi BBP_CREATE_BE_RS_NEW in order to perform your requirement.
Best Regards,
MR.