Hi, we send inspectors to the vender premises to conduct inspection before delivering the materials to our plant. inspectors spend some hours there for inspecting our product. we want to cost those hours spend for inspection. please advise how to map this.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Even if the sorce inspection is carried out at vendor premises ,we inspect the lot created at our factory only.

so what you can do is Create a task list of inspection.Use the work center in it.Assign the cost center to work center.

Also in KB21n you can book the cost ( of inspector spend for source inspection) against the cost center with activity type like "LBSH"

I hope this will add some value

Regards

Sujit

Answers (1)

Answers (1)

former_member186399
Active Contributor
0 Kudos

Hello

You can use QM orders for the same

Regards

Gajesh