Finished goods are asigned to WBS element

Former Member
0 Kudos

Hello everyone.

We use our finished goods in our Project system.

But I couldn't find the cost in our production cost report(in PS system).

What can we do in this situation.

I hope to find that cost in our report especially in production cost.

Regards.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

The plan cost for the finished good will be seen in the project after the material component is assigned to the network activity. This is dependent upon few pre-requisites:

1. The costing variant is assigned to the network header

2. The valuation variant with strategy for material valuation is defined.

3. In Transaction OPUV "determine planned costs" is mantained.

4. The "cost relevancy indicator" in the material detail screen under the network activity is ticked.

5. If Mov average price is not available, then standard cost estimate for the BOM is run.

Hope the above helps.

Regards

Srikrishna

Answers (1)

Answers (1)

Former Member
0 Kudos

This message was moderated.