cancel
Showing results for 
Search instead for 
Did you mean: 

Components vanish after planned order in is converted into production order

Former Member
0 Kudos

Dear SAP gurus,

please advise how to sort out the problem.

After update of BOM component in R/3 (usually change of the scrap factor) we observe that the component disappears after planned order conversion to production order.

Please advice how to track where exactly this happens.

Unfortunatelly it does not happen for all orders, some of the orders lose the component, others do not.

I desperately need a way to track or debug the order during conversion and CIF-ing from APO to R/3.

As far as I know there is an user exit I could activate to force BOM explosion at conversion, but would be interested to find the reason.

Your help and advise will be highly appreciated.

Thank you

BR

Ivan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Ivan,

In R/3 CFC2 give user name of on which the SNP planned orders are generated, RFC mode "Q", Logging "D" Debug "R".

Then generate the Planned orders and flow them to R/3.

Go to SMQ2 in R/3 and debug. But it will stop all the queues whichever generated on that user name.

If you want to Debug the Production order whch is flowing from R/3 to APO, then Maintain the same parameters in APo at /SAPAPO/C4.

I hope this will help you..

Regards,

Kishore Reddy

Answers (0)