hi,

in t-code nace -


> application EL----->outputtypes so many options are there like lpj1, lpj2, lmig,lpe2 etc

how to decide which ones is for Delivery schedule ?

my po is showing ravision level for material but my delivery schedule is not showing revision level for same material ?

How to solve ?

Thanks

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

SOLVED

Former Member
0 Kudos

All Consultants ...

My requirement is to Display revision level of material in Delivery schedule .

Revision Level in Purchase Order is coming for same material .

is it done through configuration / Setting.......

or In print programe or in script text part...

i have searched on net/ sdn. no info.

So need proper information...

Thanks

Former Member
0 Kudos

All Consultants ...

My requirement is to Display revision level ( FOR MATERIAL ) of material in Delivery schedule .

Revision Level in Purchase Order (FOR SAME MATERIAL )is coming for same material .

is it done through configuration / Setting.......

or In print programe or in script text part...

i have searched on net/ sdn. no info.

So need proper information...

Thanks

Former Member
0 Kudos

Hi,

My requirement is to Display revision level ( FOR MATERIAL ) of material in Delivery schedule .

Revision Level in Purchase Order (FOR SAME MATERIAL )is coming .

is it done through configuration / Setting.......

or In print programe or in script text part...

i have searched on net/ sdn. no info.

So need proper information...

Thanks

Former Member
0 Kudos

Hi,

My requirement is to Display revision level ( FOR MATERIAL ) of material in Delivery schedule .

Revision Level in Purchase Order (FOR SAME MATERIAL )is coming .

is it done through configuration / Setting.......

or In print programe or in script text part...

i have searched on net/ sdn. no info.

So need proper information...

Thanks

Former Member
0 Kudos

How to get material revision level in Delivery schedule.....

Former Member
0 Kudos

Hi all,

Can any one give me some clue on Revision Level / change number.

Want to Display revision level ( FOR MATERIAL ) of material in Delivery schedule .

Revision Level in Purchase Order (FOR SAME MATERIAL )is coming .

is it done through configuration / Setting.......

or In print programe or in script text part...

i have searched on net/ sdn. no info.

So need proper information...

Thanks

Former Member
0 Kudos

Want to Display revision level ( FOR MATERIAL ) of material in Delivery schedule .

Former Member
0 Kudos

hi all , Text Editor my code is followings:

= <K><K> Material &EKPO-EMATN& &EKPO-TXZ01&</></>

the above code give the output as

Material T01156 Spring with left curve

When i do some changes in code like folowings :

= <k><k><K> Material &EKPO-EMATN& &EKPO-REVLV& &EKPO-TXZ01&</></></>

1)will it show like this

Material T01156 B Spring with left curve

2) i want like this

Material T01156 /B Spring with left curve

Whow to add / in text additor script

Former Member
0 Kudos

Hi sir , need info

Text Editor my code is followings:

= <K><K> Material &EKPO-EMATN& &EKPO-TXZ01&

the above code give the output as

Material T01156 Spring with left curve

When i do some changes in code like folowings :

= <k><k><K> Material &EKPO-EMATN& &EKPO-REVLV& &EKPO-TXZ01&

1)will it show like this

Material T01156 B Spring with left curve

2) i want like this

Material T01156 /B Spring with left curve

Whow to add / in text additor script

Former Member
0 Kudos

Hi sir , need info

Text Editor my code is followings:

= <K><K> Material &EKPO-EMATN& &EKPO-TXZ01&

the above code give the output as

Material T01156 Spring with left curve

When i do some changes in code like folowings :

= <k><k><K> Material &EKPO-EMATN& &EKPO-REVLV& &EKPO-TXZ01&

1)will it show like this

Material T01156 B Spring with left curve

2) i want like this

Material T01156 /B Spring with left curve

Whow to add / in text additor script

Former Member
0 Kudos

in general for sheduling agrement we will use the below one

LPET SchedAgrmtSchedLine

check in messages or remove form in all other output types and check .

regards,

venkat

Former Member
0 Kudos

thanks for kind reply .

Is Delivery schedule is Purchase Order ( Medruck ) prog . ith is working on some conditions ?

Or we have different Programe name for Delivery schedule ( Print Prog and layout prog )

Thanks

Former Member
0 Kudos

it contains two things Driver program and form. form may be a script or smartform that you can able to differentiate if you observe in NACE output types

regards,

venkat.

Former Member
0 Kudos

ok sir,

my main issue is Purchase Order is showing ravision level for material like ( t00001 B )but my delivery schedule is not showing revision level for same material like ( t00001 ) ( here B is missing ) how to solve this issue ?

Former Member
0 Kudos

Hi,

How to get Revision Level : Purchase Order is showing ravision level for material like ( t00001 B )but my delivery schedule is not showing revision level for same material like ( t00001 ) ( here B is missing )

Thanks