on 10-15-2009 8:27 AM
Hi,
Can we create purchase requisitions in proman directly.
We have the project structure in which the materials are attached as stock items which generates the reservations.
We can see the same in CNMM, now we want to create the purchase requisition directly of partial quantities directly from there.
Is this a possible.
regards,
A S
We can conclude that PROMAN do not support creation of Purchase requisition from Reservataion .
Anyway Thanks !
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Maintain Stock as project stock, Select Procurement indicator such that, it will create only Reservations for WBS, then run MRP for the project, PR(PR or Planned order) will be created for the reservations. If procurement type F is maintained in material master PR will be generated during MRP
Edited by: Ahmed Rifaee on Oct 15, 2009 2:04 PM
Hi,
Yes you can create PRs from CNMM. It is basically meant for Project Oriented procurement.
Please refer the link on Executing Functions of Proman,
http://help.sap.com/saphelp_erp60/helpdata/en/d7/b8853488601e33e10000009b38f83b/frameset.htm
Regards,
Kabir
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.