on 10-15-2009 8:08 AM
Hi,
We have configured cproject in order to hours are entered by CAT2. When a employee assigned to a task enter in CAT2 see this task-WBS in his worklist ( this works OK), The problem we have found is hours assigned in cproject are not being retrieved in CAT2.
My question is, Is it possible hours planned for a resource in a task in cproject were showed in worklist in CAT2 when this resource enter as employee?
Thanks a lot for your help!!!
Sara
Check if your ECC is on EHP3 pack.
If its below that, the std Worklist doesnt support this functionality of hours from cProjects to CAT2 screen
Niranjan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Niranjan,
Thanks for your help. Yes, my ECC is on EHP3. Cproject and WBS are showed in the worklist, this works fine, but hours are empty.
For your answer I understand hours can be transfer to cproject to CAT2 worklist , If this is correct I suppouse my problem can be in CAT2 settings instead of cproject settings.
Thanks,
Sara
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.