10-15-2009 7:58 AM
HI Expert,
One month bak we had created grid values in AFS. and transfer these material to retail , in retail all selected article created with its variant.
Now problem is that when i am taking new grid value in AFS material and transfering this to retail. from AFS idoc is going in green mode.
but in retail , it is showing error message in idoc'Listing period must'Listing period must be within usability period
Message no. MH030'.
What would be cause as material is already in within usablity period.
Regards,
Santosh
10-15-2009 3:02 PM
I have checked this issue in our own test system and received the same
result.
Error Message no. MH030
The date is limited by the validity period that has generally
been defined at material level (basic data screens)
In the basic screen data you can see in the tab validity from when
the article was created. When an article is created in MM41 it is
valid from today's date
Valid From 10.01.2008 Valid to 31.12.9999
The article cannot be listed before this date, creation date of the
article. This is standard system behaviour.
10-15-2009 3:02 PM
I have checked this issue in our own test system and received the same
result.
Error Message no. MH030
The date is limited by the validity period that has generally
been defined at material level (basic data screens)
In the basic screen data you can see in the tab validity from when
the article was created. When an article is created in MM41 it is
valid from today's date
Valid From 10.01.2008 Valid to 31.12.9999
The article cannot be listed before this date, creation date of the
article. This is standard system behaviour.
10-27-2009 6:32 AM