Hi ,

We have a subcontracting scenario in R/3 . The component material is supplied to the subcontractor who manufactures the FG and sends it back to our plant . The component material is SNP planned. We want the stock of the component at subcontracting vendor(MatSub) also to be taken into consideration when the the component is planned in SNP. We have enabled the option stock at subcontractor location (forgot the exact description ) in R/3. But the stock is not getting transferred. we are currently running CCR in aPO to pust the subcontractor location stock to APO.

Am i missing some setting . Kindly help .

Accepted Solutions (0)

Answers (1)

Answers (1)

aparna_ranganathan
Active Contributor
0 Kudos

When the "vendor spec stock" option is enabled in the stock IM the stock at subcontractor location does get transferred to APO. In my test system i think there was some other data issue. But it worked in production

Thanks

Saradha