on 10-14-2009 1:22 PM
Is it possible to control delivery creation process to prevent delivery creation for "to small" volumes/values? At company code /plant level. I checked the min delivery qty in material master but this gives only warining message.
We want have control at plant/company code level. Please help us with best solution
Thanks in advance
Hi,
You cannot control this requirement at the Plant/Control level. Instead it can be controlled in the Delivery Item Category.
Filed is Check Minimum Qnty. Maintain " B " in this field.
The value you enter in the Check Minimum Quantity field determines whether you receive a warning or an error when the minimum quantity is not met. If you leave this field blank and have specifed a minimum delivery quantity, the system gives you a warning message only.
Regards,
MP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
As you have already checked the min. delivery quantity at the material master and it throws you a warning message.
Now goto the T.Code "0VLP(Zero VLP)".
Select your delivery item category.
Details.
Goto Quantity tab.
Check minimum quantity field.
Maintain the value "B" here.
Save.
If you do this,error message will be displayed.
Regards,
Krishna.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.