Hello,

In one of my sales order, if the delivery date is 14.9.09, the system confirms a zero stock on 14.09.09 but confirms the stock on 15.09.09 by cretaing a new schedule line.

How to stop this behaviour. we do not want system to propose 15.09.09 and want system to propose only 14.09.09 even it means zero stock confirmed on 14.09.09. we just need to prevent a new date in schedule line creation on 15.09.09.

there is a setting in spro in delivery sched and transp scheduling by sales doc type... will this help.. if yes shud i stop forward scheduling or uncheck "delivery "schdeuling column" and "transp sched" column..

regards

sachin

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

HI,

1.Just check 14 rth is holiday or not, if holiday u hav to do the changes in the factory calender.

2.Else use tcode VOV8 and select the sales document type for which ur creating sales order if any input is maintained in the filed Lead Time in Days just remove that.

3.else go to shipping point defination if any input is maintained in the fields Determine loading time and Determine pick/pack time just remove that.

4.Else goto Material master and remove the Planned delivaery time, In house production time, Gr processing time in MRP 2 screen.

Regards,