on 10-13-2009 1:32 PM
PS Experts,
Please guide me in the following , The below message appeared when i created a customer project in CJ20N in our new DEV server
This is the scenario
Create customer project with 3 WBSE, each one has 3 NTW and 3 activities, i maintained the cost with currency same as project curr and company code currency in the first two act.
in the third activity (General act) in cost tab i put a currency is different than project currency& company code currency and tried to save the project, the message appears.
note: Company code curr same as projet curr & controlling area curr
Is there any setting is missing in customizing
Conversion error in company code currency for general costs activity 0010
Message no. CK443
Diagnosis
For cost activity 0010, a conversion error occurred in the currency of the company code to which the material is assigned.
Procedure
Check the global settings in Customizing to be sure the exchange rate for conversion into the company code currency is correct
Thanks
Goto OPSB and select your planning profile...note down your exchange rate entered in that profile...then goto OB08, in that check whether exchange values are maintained for the currency given in activity and your company code currency.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Kabir,
Problem is Solved
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.