down payment condition type (azwr)

Former Member
0 Kudos

Hi guys,

Can you please help me how to configure AZWR (down payment) condition types. how we can raise milestone billing. please let me know.

Accepted Solutions (1)

Accepted Solutions (1)

former_member217082
Active Contributor
0 Kudos

Hi

Maintain condition type AZWR in your pricing procedure which has requirement as 2 and calc type as 48 acct key as ERL

Regards

Srinath

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Pls go through the following path:

SPRO>Sales and Distribution>Pricing-->Define and assign pricing procedures.

Assign document pricing procedures to billing types.Check the document pricing procedure assigned for your document type.

Next goto "Define Pricing Procedure Determination".

Check the pricing procedure.

Goto "Maintain pricing procedures".

Select that pricing procedure.

Click on "Control data".

Before this make sure that this condiiton type is defined using "V/06" T.Code.

Add your condition type here in this pricing procedure.

Save the entry.

If you check this in your document,it will be appeared.

Coming to billing of "milestone billing" of billing paln item,just bill each item one by one in the billing plan item.

Goto Order item details.Goto Billing plan.

Maintain the billing block for other items except the one for which you want to bill.

Bill that item using VF01 T.Code.

Regards,

Krishna.

former_member383560
Active Participant
0 Kudos

Hi

IMG configuration requires :-

1. Maintain billing plan types for milestone billing in OVBO.

2. Maintain Date Category for Billing Plan Type IN OVBJ.

3. Maintain date proposal for Billing Plan Type in OVBM.

4. Assign Billing Plan Type to Sales Documents Type in OVBP.

5. Assign Billing Plan Type to Item Categories in OVBR.

.6 Define rules for determining the date in OVBS.

7. maintain condition type AZWR with req 2, and cal type 48

For each billing date in a milestone billing plan, you can specify whether the billing

date is:

1. fixed

2. always updated with the actual date of the milestone

3. updated with the actual date of the milestone, if the date is earlier than the

planned billing date for the date

With Regards

baalakrushnan.da

Former Member
0 Kudos

thanks for giving the guide lines for configuration of AZWR FOR MILE STONE BILLING