Hi all,
When i'm creating sales order for third party i'm not getting purchase requistion number and when i'm enter third party in sales order system displaying message like " Puchase requistion can only be created for items assigned to plant. Please solve my issue.
Thanks and regards
Keshav
Yes, this message (Puchase requistion can only be created for items assigned to plant) is because of Plant field is blank at item level , As all ready Suggested..
So maintain the plant manually or maintain in CMR , MMR ,so that it will determine to sales order.
Regards,
Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
" Puchase requistion can only be created for items assigned to plant. Please solve my issue.
above message is appearing, because in line item, Plant field is blank, input the Plant or maintian the Delivering Plant either in Material Master - Sales org1 view or Customer Master data - Sales area - Shipping tab.
make sure, all the settigns for 3rd party,as said by others should be in proper. I hope as per your post n message, Plant field is blank .
try n revert
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In standard SAP, item category TAS is used for this. The schedule line category is CS. Here you can see a field 'order type' with value 'NB'. This triggers the automatic creation of the PR.
Plus in the material master also you need to do certain settings.
1) If you are always following a third party process for a material then you have to create the material using item category group BANS. The procurement type should be marked as external procurement (F) in MRP 2 view of the material master record.
2) If you are not always allowing third party order processing then you can create a material master record with item category group as NORM and the procurement type should be marked as (X) meaning both types of procurement (in house manufacturing and external procurement).
In the item category the billing relevance should be 'F'.
With Regards
baalakrushnan.da
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Keshav
Just check in MMR wheather you have maintained Purchasing tab or not , if not maintained then go to MM01 and extend the material by selecting the Purchasing View.
Secondly , also check in VOV6 wheather for the schedule line CS , document type NB has been assigned or not.
Regards
Srinath
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.