on 10-13-2009 10:42 AM
Hi,
We are generating PR of material through CJ2N. I want to make storage location filed in generatl data tab of material, mandatory as well defalut value depending upon the project. If defalult value can not come depending upon project defination then i want to make default value as blank but mandatory
How can i do this?
Regards,
Kalpesh
Hi
To make LGORT field mandatory in component screen of Network/Order you can use User Exit.
Swapnil Kharul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This can be achieved by customising the node
SPRO>Material Management>Purchasing>Purchase Requisition>Define Screen Layout at Document level>ME51Basic Data in the Field Selection Key.
Make storage location as Mandatory Field.
Please get guidance from your MM Consultant for this customisation
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Kalpesh,
In standard SAP the storage location will be an input field and no default values will get populated when you attach a material component in the activities as the material master will be extended to multiple storage locations.But in your case if is coming as default either some screen variant must exist or some parameter Id would have been maintained.Check Which & How the storage location is getting defaulted from your MM consultant.