Schedule line confirmation on next working day

pmayilvahanan
Participant
0 Kudos

Hi,

For a sales org, (IE93) in a sales order if we request delivery on 25.12.2009 (Xmas day), APO availability check is performed and it is confirming on the next/prior working day.

But in case of other sales org(GB93) it is confirming on the same day(on Xmas itself, which is a holiday)..

We want the same control for GB93 also.. Any idea?

Regards,

Mayil

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member184555
Active Contributor
0 Kudos

Hi

Check the calendars assigned to the shipping point and also to the sales organisation and see if 25th Dec is specified as holiday or not.

Regards,

Ravi

pmayilvahanan
Participant
0 Kudos

Hi,

25th is maintained as a holiday.

Even the holiday is id is shared by both calendars.

Former Member
0 Kudos

Hi,

Check the Factory calender Assignmene for these two COMPANY CODES, PLANT, in OVR3

I believe the Factory calender is different for these two Organisational Units.

Check the Factory calender settings in OVR3 transaction code

Please revert back if you need further details

thanks,

santosh

pmayilvahanan
Participant
0 Kudos

Hi Santosh,

Checked OVR3. It is perfect.

both Sales org fall under a same company code.