samples testing

raju_123
Participant
0 Kudos

During recieving insp, we issue samples for mechanical testing and we use tensile machine to test amples. please advise how to capture the sample material cost as well as operator cost of the tensile machine.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

sample material cost :

In receving Inspection during UD & stock posting put the mechanical testing and tensile testing sample in the field "sample"

In SPRO at plant level>QM>basic setting>Plant level settings-> maintain the cost center on which you want debit the cost.

So you can see the cost in T code KSBB.

This will give you material cost.

operator cost of the tensile machine

For this you have to either

1.Do manually agaist cost center through KB21n.This can be done once in a month for a machin or operator by using logic of mass upload.

2.You can maintain a task list .In task list maintain Work center.In work cemter maintain the Man & machin hrs.

when you are taking UD system will prompt you to enter the man & machin hrs.

Also maintain Cost Center in Costing view of the Work center.

I hope this will add some value

Regards

Sujit

raju_123
Participant
0 Kudos

thank u sir. i have tried to create task list thru ia05, but ther will be no material field to assign this tak list to roh material code. pls advise how to link roh material that we get from po in the task list?

Former Member
0 Kudos

Dear

What is exactly your scenario.......

The option which I have suggested was with reference to inspection type 01 & not 14

The task list you have to use is with usage 5 through QP01 & not IA01/IA05.

You need not to have a equipment task list ,a simple material task list will do

Sujit

Answers (0)