Hi guru's
Prerequisites: Plan work 260 hours. Constraints on start and finish date. Distribution rule is equal to distribution according to factory calender. For scenario 2) actual work is 100 hours. Remaining work is 160 hours. Duration of activity is 1 year.
Scenario 1) When calculating project cost forecast without any actual cost from time reporting, the cost forecast is distributed over the remaining duration of the activity.
Scenario 2) When calculating project cost forecast with actual cost from time reporting, the cost forecast is planned on the same period as the forecast report is run. We would like this to be done in the same way as in scenario 1 above.
If someone out there has experience of this issue, we appeciate your advice.
Best Regards
Bo
Hi,
Thanks for your reply. We have already tried this option and it did not solve our problem.
BR
Bo
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In the TCode: CJ9L, you have the option: set date (CTRL+F2) please set the date as per your requirement.
Hope it helps...
Thanks!!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.