Need to add Plant and CostCenter as Selection fileds of CJI3 Initial screen

Former Member
0 Kudos

Hello Team,

Can you suggest me OSS note or User exit to add Plant and CostCnters as selection criteria for CJI3 Actual cost line Items report.

Thanks in advance,

Best regards,

Harish.P

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

In CJI3, press Shift+F4, you will get dynamic selection screen, there under Org.units definition you can give values for Plant or Cost center, this will filter out the input projects with that plant and cost center value.

Former Member
0 Kudos

This will restrict the data corresponds to the selection you have made in the dynamic selection, but you cannot run the report with these dynamic selection itself.

I need to run the report with Plant and CostCenters as selection criteria itself.

Regards,

Harish.P

former_member203108
Active Contributor
0 Kudos

Dear, CJI3 is Project Actual Cost Line Items report, so your input should be project, not a plant or cost center. If you want Cost center ACtual line items then you can use KSB1

Former Member
0 Kudos

Hi,

Please refer Note. 331416, 325546.

Regards,

Kabir

Former Member
0 Kudos

Harisha

I agree with above reply but your requirement sounds a bit weird.

Note sure if cost element reports are any useful for your requirement.

Look (refer note) at the report painter option ( but you might still need to enter the Project/WBS)

Note 668513 - FAQ 2: Cost element reports in Project System

Regards

Sreenivas

Answers (1)

Answers (1)

Former Member
0 Kudos

User exit COOMEP01 component EXIT_SAPLKAEP_001.