Dear All,
Can you please let me know the object that governs the projct TECO Status.
Thanks
Hi,
TECO is a system status which is pre defined in the system and can be set on to WBS, project definition for a project. Also Network and its activities can also be set to TECO status independently.
If TECO status is set on a project definition then it will make all the subordinate WBS elements and networks for a project in TECO status.
TECO status will not allow any planning activity but can allow the posting of revenues and account assignment activities.
But as you have asked that which object governs the TECO status for a project , In this case it can be a project definition made TECO from the top , and can be a WBS element made TECO individually.
Thanks
DHRUV KUMAR MALHOTRA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
question is not clear
TECO is a system status that can be set on various objects in PS like network Activity, WBS etc
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.