Hi SNC Experts ,
We were planning to build an SNC demo in our internal systems.I want to know if 2 months is a reasonable timeline to configure SNC and integrate it with ECC .
The scenarios we are looking at is
SNC for Forecast Capture .
Inventory Tracking
Customer Collaboration
We want to build this demo for abt 2 locations.
Let me know if it is a reasonable timeline.
Thanks in advance for your replies.
Regards,
Ranjini.
Hi Ranjini,
Majority of your time will go in setup of SNC for Forecast Capture (3 week)& Inventory Tracking (3 week). Customer Collaboration should take (2 week)
As per my experience, Take 2 week buffer in case you get stuck in any system related issue
Awards points if you find it useful
Regards
Rohit Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ranjini,
It depends on whether the system is ready by assuming there no issue from basis or XI it reasonable time line.
You can configure SNC and integrate it with ECC .
As per SAP for SNC for Forecast Capture,Inventory Tracking,Customer Collaboration time line is 9 weeks
Limits of Pilot Scope:
1u20133 plants, <= 3 customers, <= 200 products
Thanks,
Nikhil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.