i have added an external activity with contract in a project with period one year
how can i distribute the planned cost in periods from 1 to 12
Thanks for all
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You have to maintain an invoicing plan, after that the cost of that external activity will be distributed as per the invoicing plan. you can refer this http://help.sap.com/saphelp_erp60_sp/helpdata/en/4c/226f8d46e611d189470000e829fbbd/content.htm