Sales Based Settlement - Due Dates Variance

Former Member
0 Kudos

Hi Folks

Here's the situation..

I have a Sales Based Contract (Lease-Out) with 1 Reporting Rule and its Sales Rule for which the frequency is given as 7 days.

Though the Sales Reports are being made weekly, if the Settlment is made weekly or monthly the due date is calculated as monthly if checked in the conditions cash flow. Now after the fiscal year is passed, the same due dates are varied as of a sudden to weekly.

i.e. for a given contract say 1000/1010101 in PRD when the same contract in QAS is settled in passed on fiscal year, the due date is changed to weekly from monthly in the cash flow. All the frequencies set to the conditons are standard and found same within PRD & QAS.

Please let me know if my question is not clear.

Regards

Sekhar

Edited by: Sekhar M on Nov 9, 2009 6:09 PM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

"Baseline payment dte" in Parameters tab acts as manual due date for the settlement (RESRSE).

Edited by: Sekhar M on Nov 9, 2009 6:12 PM