Easy Cost Planning

Former Member
0 Kudos

Dear PS PALS

Is it possible by some means to have EASY COST PLANNING period based also along with CE based? Has anybody found the way out to add period dimension in ECP as it is Cost element based only.

Best Regards

Adwait

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Easy cost planning is cost element based and in the CJ40, the periodic amount can be seen there.

Regards,

Uddhab