on 10-07-2009 12:50 PM
Dear experts
We are planning to upgrade our exitsting XI 3.0 to PI7.0.
Due to system requeriments, we need to install PI on new hardware and migrate all the existing scenario's from XI 3.0 PI7.'0
How to migrate the existing ABAP developements from XI to PI ?
It's possible to export scenarios from XI and import them into PI?
Thanks, in advance
Carme
Hi,
you should go to PI 7.1 and not PI 7.0 otherwise it makes not so much sense.
And yes it's possible to migrate your scenarios. If you have UDFs you have to check them because the java version has changed.
Regards
Patrick
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Guess this could be helpful...
http://www.sdn.sap.com/irj/scn/index?rid=/library/uuid/90baf3dd-dbf9-2b10-47aa-ac5f56bb5030
Regards
Patrick